Survey · Engineering · Execution · O&M

How a plant gets built.

Every project runs through the same four stages, in the same order. Nothing is skipped to hit a price, and nothing is handed to a third party we cannot stand behind. Here is exactly what happens, and who does it.

Stage 01

Basic survey & statutory approvals

Before anything is quoted, we establish whether the site can actually produce what you are being promised — and whether the paperwork will allow it.

  • Radiation data analysis using PVsyst for the specific coordinates of your site, not a district average.
  • NOC and design approval prepared and pursued with the DISCOM, including the sanctioned-load check.
  • Technical & commercial feasibility — shadow analysis, roof or ground condition, structure capacity, and honest payback maths.
  • Basic layout and single line diagram so the electrical design is fixed before procurement begins.

What you receive

A yield estimate you can hold us to, a bill of materials, and the approval route with realistic timelines.

Why it matters

Most underperforming plants in this region were undersized, over-shaded or wrongly approved — all of which are decided at this stage.

Stage 02

Engineering & procurement

The detailed design, and then the buying. Because we do both, the design is not quietly compromised later to match whatever material was cheapest that month.

  • PV array design and module selection — string sizing, orientation, tilt and row spacing worked out for the site.
  • Balance of plant design covering combiner boxes, protection, earthing and lightning arrest.
  • Inverter selection and sizing against the DC array ratio and the local voltage profile.
  • Civil and structural work — foundations and mounting engineered for local wind load.
  • LT and HT cabling specified on voltage drop, not on the lowest per-metre rate.
  • Electrical works up to and including the metering interface.

Stage 03

Project execution, erection & commissioning

The stage where most timelines slip. Ours is run as a managed construction project with a schedule you can see, not as a delivery of boxes followed by a scramble.

  • Construction management on site — one point of responsibility for structure, modules, cabling and inverters.
  • Schedule monitoring against the agreed programme, with progress reported to you rather than on request.
  • Coordination of clearances — inspection, net-meter installation and final commissioning approval chased to closure.
  • Safety-trained crew for work at height and live electrical work.

See the system types we commission

Week 1

Mobilisation

Site handover, material staging, structure marking and foundation work begin.

Week 2–3

Erection

Mounting structure completed, modules laid and clamped, DC strings dressed and tested.

Week 4

Electrical

Inverters, combiner boxes, earthing, lightning arrest and AC cabling to the metering point.

Handover

Commissioning

Inspection, net meter, first generation report, and the documentation set for your records.

Stage 04

Operations & maintenance

A solar plant is a twenty-five year asset, and it quietly loses output every year it is left alone. Our O&M keeps the generation curve where the design said it would be.

Daily performance monitoring

Generation is checked against the expected yield for that day and that weather. A drop gets investigated, it does not get averaged away over the month.

Preventative maintenance

Scheduled inspection of connections, protection devices, earthing and structure — before a loose termination becomes a burnt one.

Warranty management

We hold the manufacturer warranty paperwork and pursue module and inverter claims on your behalf, which is the part owners almost never win alone.

Module washing

Dust in this region is the single largest recoverable loss. Cleaning is scheduled by season, not by complaint.

Trained staff

Our people are trained on safety, performance and quality — the three things that decide whether a plant lasts its full life.

One point of contact

The same team that built the plant maintains it. Nothing gets lost in a handover to a subcontractor you have never met.

Process questions

The things owners ask us first.